Progress in figures
Activity30-Sep-1528-Oct-1511-Nov-1605-Dec-1611-Jan-1713-Feb-17
Proposed site locations identified 38 39 38 38 37 37
Sites surveyed 35 36 38 38 36 36
Landowner agreement in principle 33 34 36 37 36 36
Planning application submitted 25 28 28 28 28 28
Planning application validated 21 14 12 9 7 6
Planning permission received 10 14 14 22 22 24
Leases with Landowners - - 19 15 16 16
Leases signed off - - 6 8 9 11
Concrete mast base constructed nil 1 1 3 5 5
Mast constructed nil nil nil nil nil 4
Mast live nil nil nil nil nil nil